Upgrade to CockroachDB v22.1

On this page Carat arrow pointing down
Warning:
CockroachDB v22.1 is no longer supported. For more details, see the Release Support Policy.

Because of CockroachDB's multi-active availability design, you can perform a "rolling upgrade" of your CockroachDB cluster. This means that you can upgrade nodes one at a time without interrupting the cluster's overall health and operations.

This page describes how to upgrade to the latest v22.1 release, v22.1.22. To upgrade CockroachDB on Kubernetes, refer to single-cluster or multi-cluster instead.

Terminology

Before upgrading, review the CockroachDB release terminology:

  • A new major release is performed every 6 months. The major version number indicates the year of release followed by the release number, which will be either 1 or 2. For example, the latest major release is v23.2 (also written as v23.2.0).
  • Each supported major release is maintained across patch releases that fix crashes, security issues, and data correctness issues. Each patch release increments the major version number with its corresponding patch number. For example, patch releases of v23.2 use the format v23.2.x.
  • All major and patch releases are suitable for production usage, and are therefore considered "production releases". For example, the latest production release is v23.2.2.
  • Prior to an upcoming major release, alpha and beta releases and release candidates are made available. These "testing releases" are not suitable for production usage. They are intended for users who need early access to a feature before it is available in a production release. These releases append the terms alpha, beta, or rc to the version number.
Note:

There are no "minor releases" of CockroachDB.

Step 1. Verify that you can upgrade

Run cockroach sql against any node in the cluster to open the SQL shell. Then check your current cluster version:

icon/buttons/copy
> SHOW CLUSTER SETTING version;
Note:

If you are upgrading from any cluster version prior to v21.1, then before upgrading from v20.2 to v21.1, you must ensure that any previously decommissioned nodes are fully decommissioned. Otherwise, they will block the upgrade. For instructions, see Check decommissioned nodes.

To upgrade to v22.1.22, you must be running either:

  • Any earlier v22.1 release: v22.1.0-alpha.1 to v22.1.21.

  • A v21.2 production release: v21.2.0 to v21.2.17.

If you are running any other version, take the following steps before continuing on this page:

Version Action(s) before upgrading to any v22.1 release
Pre-v22.1 testing release Upgrade to a corresponding production release; then upgrade through each subsequent major release, ending with a v21.2 production release.
Pre-v21.2 production release Upgrade through each subsequent major release, ending with a v21.2 production release.
v21.2 testing release Upgrade to a v21.2 production release.

When you are ready to upgrade to v22.1.22, continue to step 2.

Step 2. Prepare to upgrade

Before starting the upgrade, complete the following steps.

Check load balancing

Make sure your cluster is behind a load balancer, or your clients are configured to talk to multiple nodes. If your application communicates with a single node, stopping that node to upgrade its CockroachDB binary will cause your application to fail.

Check cluster health

Verify the overall health of your cluster using the DB Console:

  • Under Node Status, make sure all nodes that should be live are listed as such. If any nodes are unexpectedly listed as SUSPECT or DEAD, identify why the nodes are offline and either restart them or decommission them before beginning your upgrade. If there are DEAD and non-decommissioned nodes in your cluster, it will not be possible to finalize the upgrade (either automatically or manually).

  • Under Replication Status, make sure there are 0 under-replicated and unavailable ranges. Otherwise, performing a rolling upgrade increases the risk that ranges will lose a majority of their replicas and cause cluster unavailability. Therefore, it's important to identify and resolve the cause of range under-replication and/or unavailability before beginning your upgrade.

  • In the Node List:

    • Make sure all nodes are on the same version. If any nodes are behind, upgrade them to the cluster's current version first, and then start this process over.
  • In the Metrics dashboards:

    • Make sure CPU, memory, and storage capacity are within acceptable values for each node. Nodes must be able to tolerate some increase in case the new version uses more resources for your workload. If any of these metrics is above healthy limits, consider adding nodes to your cluster before beginning your upgrade.

Check decommissioned nodes

If your cluster contains partially-decommissioned nodes, they will block an upgrade attempt.

  1. To check the status of decommissioned nodes, run the cockroach node status --decommission command:

    icon/buttons/copy
    cockroach node status --decommission
    

    In the output, verify that the value of the membership field of each node is decommissioned. If any node's membership value is decommissioning, that node is not fully decommissioned.

  2. If any node is not fully decommissioned, try the following:

    1. First, reissue the decommission command. The second command typically succeeds within a few minutes.
    2. If the second decommission command does not succeed, recommission and then decommission it again. Before continuing the upgrade, the node must be marked as decommissioned.

Review breaking changes

Review the backward-incompatible changes in v22.1 and deprecated features. If any affect your deployment, make the necessary changes before starting the rolling upgrade to v22.1.

Step 3. Decide how the upgrade will be finalized

Note:

This step is relevant only when upgrading from v21.2.x to v22.1. For upgrades within the v22.1.x series, skip this step.

By default, after all nodes are running the new version, the upgrade process will be auto-finalized. This will enable certain features and performance improvements introduced in v22.1. However, it will no longer be possible to roll back to v21.2 if auto-finalization is enabled. In the event of a catastrophic failure or corruption, the only option will be to start a new cluster using the previous binary and then restore from one of the backups created prior to performing the upgrade. For this reason, we recommend disabling auto-finalization so you can monitor the stability and performance of the upgraded cluster before finalizing the upgrade, but note that you will need to follow all of the subsequent directions, including the manual finalization in step 5:

  1. Upgrade to v21.2, if you haven't already.

  2. Start the cockroach sql shell against any node in the cluster.

  3. Set the cluster.preserve_downgrade_option cluster setting:

    icon/buttons/copy
    > SET CLUSTER SETTING cluster.preserve_downgrade_option = '21.2';
    

    It is only possible to set this setting to the current cluster version.

Features that require upgrade finalization

When upgrading from v21.2 to v22.1, certain features and performance improvements will be enabled only after finalizing the upgrade, including but not limited to:

  • SCRAM-SHA-256 authentication: CockroachDB supports SCRAM-SHA-256 authentication for clients in both CockroachDB Cloud and CockroachDB Self-Hosted. For SQL client sessions, it is now possible to use the authentication methods password (cleartext passwords), and cert-password (TLS client cert or cleartext password) with either CRDB-BCRYPT or SCRAM-SHA-256 stored credentials.
  • Row-Level Time to Live (TTL): CockroachDB has preview support for Time to Live ("TTL") expiration on table rows, also known as Row-Level TTL. Row-Level TTL is a mechanism whereby rows from a table are considered "expired" and can be automatically deleted once those rows have been stored longer than a specified expiration time.

For an expanded list of features included in the v22.1 release, see the v22.1 release notes.

Step 4. Perform the rolling upgrade

Tip:

Cockroach Labs recommends creating scripts to perform these steps instead of performing them manually.

Follow these steps to perform the rolling upgrade. To upgrade CockroachDB on Kubernetes, refer to single-cluster or multi-cluster instead.

For each node in your cluster, complete the following steps. Be sure to upgrade only one node at a time, and wait at least one minute after a node rejoins the cluster to upgrade the next node. Simultaneously upgrading more than one node increases the risk that ranges will lose a majority of their replicas and cause cluster unavailability.

Warning:

After beginning a major-version upgrade, Cockroach Labs recommends upgrading all nodes as quickly as possible. In a cluster with nodes running different major versions of CockroachDB, a query that is sent to an upgraded node can be distributed only among other upgraded nodes. Data accesses that would otherwise be local may become remote, and the performance of these queries can suffer.

These steps perform an upgrade to the latest v22.1 release, v22.1.22.

  1. Drain and shut down the node.

  2. Download and install the CockroachDB binary you want to use:

    icon/buttons/copy

    $ curl https://binaries.cockroachdb.com/cockroach-v22.1.22.darwin-10.9-amd64.tgz|tar -xzf -
    

    icon/buttons/copy

    $ curl https://binaries.cockroachdb.com/cockroach-v22.1.22.linux-amd64.tgz|tar -xzf -
    

  3. If you use cockroach in your $PATH, rename the outdated cockroach binary, and then move the new one into its place:

    icon/buttons/copy

    i="$(which cockroach)"; mv "$i" "$i"_old
    
    icon/buttons/copy
    $ cp -i cockroach-v22.1.22.darwin-10.9-amd64/cockroach /usr/local/bin/cockroach
    

    icon/buttons/copy

    i="$(which cockroach)"; mv "$i" "$i"_old
    
    icon/buttons/copy
    $ cp -i cockroach-v22.1.22.linux-amd64/cockroach /usr/local/bin/cockroach
    

  4. Start the node to have it rejoin the cluster.

    Without a process manager like systemd, re-run the cockroach start command that you used to start the node initially, for example:

    icon/buttons/copy
    $ cockroach start \
    --certs-dir=certs \
    --advertise-addr=<node address> \
    --join=<node1 address>,<node2 address>,<node3 address>
    

    If you are using systemd as the process manager, run this command to start the node:

    icon/buttons/copy
    $ systemctl start <systemd config filename>
    
  5. Verify the node has rejoined the cluster through its output to stdout or through the DB Console.

  6. If you use cockroach in your $PATH, you can remove the old binary:

    icon/buttons/copy
    $ rm /usr/local/bin/cockroach_old
    

    If you leave versioned binaries on your servers, you do not need to do anything.

  7. After the node has rejoined the cluster, ensure that the node is ready to accept a SQL connection.

    Unless there are tens of thousands of ranges on the node, it's usually sufficient to wait one minute. To be certain that the node is ready, run the following command:

    icon/buttons/copy
    cockroach sql -e 'select 1'
    

    The command will automatically wait to complete until the node is ready.

  8. Repeat these steps for the next node.

Step 5. Roll back the upgrade (optional)

If you decide to roll back to v21.2, you must do so before the upgrade has been finalized, as described in the next section. It is always possible to roll back to a previous v22.1 version.

To roll back an upgrade, do the following on each cluster node:

  1. Perform a rolling upgrade, as described in the previous section, but replace the upgraded cockroach binary on each node with the binary for the previous version.
  2. Restart the cockroach process on the node and verify that it has rejoined the cluster before rolling back the upgrade on the next node.
  3. After all nodes have been rolled back and rejoined the cluster, finalize the rollback in the same way as you would finalize an upgrade, as described in the next section.

Step 6. Finish the upgrade

Note:

This step is relevant only when upgrading from v21.2.x to v22.1. For upgrades within the v22.1.x series, skip this step.

If you disabled auto-finalization in step 3, monitor the stability and performance of your cluster for as long as you require to feel comfortable with the upgrade (generally at least a day). If during this time you decide to roll back the upgrade, repeat the rolling restart procedure with the old binary.

Once you are satisfied with the new version:

  1. Run cockroach sql against any node in the cluster to open the SQL shell.

  2. Re-enable auto-finalization:

    icon/buttons/copy
    > RESET CLUSTER SETTING cluster.preserve_downgrade_option;
    
    Note:

    This statement can take up to a minute to complete, depending on the amount of data in the cluster, as it kicks off various internal maintenance and migration tasks. During this time, the cluster will experience a small amount of additional load.

  3. Check the cluster version to confirm that the finalize step has completed:

    icon/buttons/copy
    > SHOW CLUSTER SETTING version;
    

Troubleshooting

After the upgrade has finalized (whether manually or automatically), it is no longer possible to downgrade to the previous release. If you are experiencing problems, we therefore recommend that you:

  1. Run the cockroach debug zip command against any node in the cluster to capture your cluster's state.

  2. Reach out for support from Cockroach Labs, sharing your debug zip.

In the event of catastrophic failure or corruption, the only option will be to start a new cluster using the old binary and then restore from one of the backups created prior to performing the upgrade.

See also


Yes No
On this page

Yes No